On September 26, ODOT’s Transportation Review and Advisory Council
(TRAC) met and
approved the “Final 2014-2017 Major New Program List” of projects. The list includes
the projects previously approved by the Ohio Turnpike and Infrastructure
Commission (OTIC) to be financed with turnpike bonds. The final list of
projects approved in the TMACOG planning area includes the following:
- McCord Road grade separation; $31.6 million estimate, TRAC allocates $3.3 million, FY 2014 start construction
- I-75 widening from SR 199/SR 25 (Perrysburg) to CR 99 (Findlay); $195.4 million estimate, $193 million TRAC (OTIC bonds), FY 14 start construction
- I-75/I-475 Interchange upgrade phase 2 (Jeep Split); $175.9 million estimate, $163 million TRAC ( OTIC bonds), FY 15 start construction
- I-75 widening from Phillips to I-280; $51 million estimate, $45 million TRAC (OTIC bonds), FY 15 start construction
- I-475/US 20 interchange upgrade (Central Ave. interchange); $59 million estimate, $44.0 million TRAC ( OTIC bonds), FY 15 start construction
The total cost of the above projects is $512.9 million with a TRAC
funding commitment of $448.3 million programmed for 2014 and 2015 fiscal year construction. Of the total $970 million available from the
sale of OTIC bonds, $422.9 million will be committed to projects in the TMACOG MPO
planning area of Lucas and Wood counties.